PB providing CM for Chicago Blue Line 

CHICAGO – The Chicago Transit Authority (CTA) awarded a construction management contract to Parsons Brinckerhoff (PB) for a rail replacement and tunnel rehabilitation project on the system’s Blue Line subway, which connects the downtown business district with O’Hare International Airport.

The $88 million project is one of the first in Chicago to be fully funded by the American Recovery and Reinvestment Act of 2009. It involves replacement of 31,000 existing wooden half ties with new concrete half ties and 6,200 track feet of stone ballast with new concrete slab and direct fixation fasteners. The project also includes installation of 29,000 track feet of new rail and the installation of 44,000 linear feet of new contact rail. Additionally, two track crossovers will be rebuilt, all lighting and drainage systems along the route will be cleaned, and some structural repairs will be performed in the 4-mile-long Dearborn Blue Line subway tunnel.

As the construction manager, PB is responsible for schedule and cost control and quality/safety assurance, as well as construction supervision, inspection, and documentation.

Because of heavy traffic on the Blue Line, most track and tunnel rehabilitation work will be performed during weekend track outages. The project is scheduled to be completed in March 2010.

Related Engineering Channels




Headlines From Around The Web

Paved, but Still Alive (New York Times)
Blog: Panama Canal Expansion: A Game Changer (Transportation Issues Daily)
Plans envision Pittsburgh 'Aerotropolis' (Pittsburgh Business Times)
GAI Consultants Makes Acquisition (Inside Indiana Business)






Current Issue


Exclusive

Civil engineering industry outlook - Part 1

While 2011 didn't offer too much progress in an economic turnaround, it seems that many people in the architecture, engineering, planning (A/E/P) and environmental consulting industries are adjusting to challenges. For 2012, increased stability is expected, although large changes don't seem likely.


New & Noteworthy


Progressive Engineering


Editor's Comment


ZweigWhite Upcoming Events

Environmental Connection 2012
Date: February 26, 2012 - February 29, 2012
Location: Las Vegas

Principals Academy
Date: March 8, 2012 - March 9, 2012
Location: Ft. Lauderdale FL

Geosynthetic Reinforced Retaining Wall Failures and Their Remediation
Date: March 13, 2012 - March 13, 2012
Location: Folsom PA

2012 Sustainable Water Management Conference
Date: March 18, 2012 - March 21, 2012
Location: Portland OR

Ninth National Conference on Transportation Asset Management
Date: April 16, 2012 - April 18, 2012
Location: San Diego


Events